肖鸿斌, 金耀岷. 深埋串珠状溶洞的超高层基础设计案例分析[J]. 中国岩溶, 2023, 42(2): 382-390. doi: 10.11932/karst20230209
引用本文: 肖鸿斌, 金耀岷. 深埋串珠状溶洞的超高层基础设计案例分析[J]. 中国岩溶, 2023, 42(2): 382-390. doi: 10.11932/karst20230209
XIAO Hongbin, JIN Yaomin. Case study on super high-rise foundation design of the deep-buried beaded karst cave[J]. Carsologica Sinica, 2023, 42(2): 382-390. doi: 10.11932/karst20230209
Citation: XIAO Hongbin, JIN Yaomin. Case study on super high-rise foundation design of the deep-buried beaded karst cave[J]. Carsologica Sinica , 2023, 42(2): 382-390. doi: 10.11932/karst20230209

超高层建筑对地基稳定性、地基承载力和地基变形的要求非常高。2007年某市拟建超高层建筑,详勘揭露地表80 m以下地层中分布深埋串珠状溶洞,溶洞顶板厚度薄,串珠状溶洞在水平方向和垂直方向的分布情况及连通性等方面的不确定性较多,若建筑基础浅埋,则地基承载力无法满足设计要求;若建筑基础深埋,则因套管回收及溶洞处理等问题施工的可行性差。设计原则最终确定为基础浅埋方案,首先初步确定满足地基稳定性的前提条件,随后工程设计及施工各专业围绕单桩承载力问题进行讨论并修改专业方案,最终决定应用当时的创新工艺−灌注桩后注浆工艺解决单桩承载力问题。该工程终于在2010年得以推进。工程一期建成后平均沉降与不均匀沉降均很好地满足了规范要求。此次多专业技术联动是勘察设计施工技术一体化的一次成功尝试,相比目前质量进度管理一体化更具前瞻性,也是今后技术优化一体化的发展方向。

超高层建筑 深埋串珠状溶洞 地基稳定性 覆盖层厚度 灌注桩后注浆工艺 多专业技术联动 勘察设计施工技术一体化

In 2007, a super high-rise building was proposed in a city. A detailed survey revealed the distribution of deep-buried beaded karst cave in the stratum under the surface of 80 meters. The construction of the proposed super high-rise building highly requires foundation stability, bearing capacity and deformation. The geological conditions of the site are complex because the site is irregularly distributed with deep-buried beaded karst caves with thin roofs in multiple layer. Geophysical exploration was conducted to prove that the burial depth of karst caves is likely to be deepened. There are many uncertainties in the horizontal and vertical distribution and connectivity of beaded karst caves. Because of the deep burial depth, the situation of groundwater cannot be accurately identified. If the foundation is shallowly buried and meets the demand of stability, its bearing capacity will not satisfy the requirement. Besides, the effective pile length is very limited, and the bearing capacity of a single pile cannot meet the design requirements. If the foundation is deeply buried, foundation piles will be fixed crossing the karst cave in each layer and entering the lower stable bedrock. Before design and construction, the construction survey should be conducted pile by pile, and foundation treatment such as grouting should be carried out for the karst cave in each layer within the range of pile shaft. However, the site survey has indicated that the recovery of 80-meter casing pipe was very difficult and even impossible for many pipes. The indeterminacy in vertical and horizontal distribution and in connectivity of karst caves was relatively large, leading to the inaccurate estimation of grouting volume, poor construction feasibility, and unavailability of managed cost. In order to address the indeterminacy of karst cave distribution—the biggest construction difficult, the shallow-buried design principle of the foundation was finally determined.

According to the idea that the foundation should be shallowly buried and meet the requirement of bearing capacity as well, in the aspect of survey, the precondition for the foundation stability requirement—the deepest burial depth of each unit—was preliminary determined. Based on the distribution characteristics of karst caves, roof thicknesses and cavity distribution depths of different units, the survey was carried out by qualitative method and semi-quantitative method. It was also recommended to transform the foundation stability problem into an uneven foundation problem according to the normative framework. In terms of structural design, the foundation stability scheme was further defined through calculation, and accordingly the structure was redesigned to determine the structure model. From the perspective of architectural design, the professional scheme was revised to reduce the burial depth of the basement from the original 20 m to 12 m according to the shallow burial depth. The difficulty of shallow-buried scheme was focused on the bearing capacity of a single pile, and hence this problem was discussed in terms of architectural design. In order to reduce the bearing capacity of a single pile, the team for architectural design decided to use steel structure frame to reduce the upper load. In terms of structural design, the steel-framed shear wall and light-weight partition wall were used to reduce the wall thickness and structural dead weight and other loads. Two layers of reinforcement were adopted to increase the overall structural stiffness so as to control the uneven settlement. Although the design scheme was revised repeatedly to minimize the bearing capacity of a single pile, it still could not meet the design requirements; consequently, the construction was postponed. In order to successfully solve the problem of bearing capacity of a single pile, we visited the survey expert for foundation scheme and were recommended the new process of post-grouting for cast-in-place piles, which was still an innovation in 2007. In this process, the grouting of pile ends and pile sides after piling reinforces the soil around the ends and sides, and thus effectively increasing their resistance. In this way, this process greatly improved the bearing capacity of a single pile, and at the same time controlled the uneven settlement. The project of super high-rise building was finally carried forward in 2010.

After the first phase of the project was completed, the average settlement and uneven settlement of Tower I well met the design requirements according to the settlement observation data during and after the construction. This complex project involved multi-disciplinary technical linkage including the deep integration of professional expertise from architectural design, survey, structural design and construction, which is a successful attempt on technology integration of survey, design and construction. Compared with the current integration of management progress, this technology is more complex and forward-looking. It is not only an innovation in the construction management process, but also shows a development direction for the future integration of technology optimization.

super high-rise building deep-buried beaded karst cave foundation stability overburden thickness post grouting process of cast-in-place pile multi-disciplinary technical linkage integration of survey, design and construction technology 层
序土层
名称层顶埋深
/m双桥静探
锥尖/侧壁标
贯波
速MPa·kPa −1 击m·s −1 ②粉质黏土1.5~2.51.23/61.618.5160③粉质黏土5.5~7.01.32/37.548.2178④粉质黏土8.5~10.51.16/22.235.5178⑤ 1 粉质黏土13.5~15.52.10/74.2712.6231⑤ 2 黏土17.5~19.02.51/116.716.7262⑥ t 粉土22.0~25.05.31/92.1816.1248⑥粉质黏土23.0~26.02.15/68.7914.3267⑦ 1 粉质黏土28.0~30.01.44/30.827.6233⑦ 2 粉质黏土33.0~35.01.29/37.516.7233⑧粉质黏土38.0~40.02.32/78.2515.2320⑧ t 粉土41.5~44.08.51/111.121.5310⑨粉土50.0~52.07.90/167.728.1336⑩黏土55.0~57.03.71/140.322.2341⑾ 1-1 粉土60.0~62.010.3/202.930.9396⑾ 1-2 粉质黏土60.0~65.04.54/111.720.4425⑾ 2 粉质黏土69.0~71.03.24/81.9518.0589⑿黏土75.0~77.05.81/151.836.7612